Table 4 - Changing dPRs that have NOT been fully approved
Table 5 - Changing dPRs that have been fully approved
Table 6 - Changing dPRs when the PO exceeds the dPR
Table 4 - Changing dPRs that have not been fully approved
This table outlines the procedures for changing certain information on
dPRs after they've been created but before they are fully approved.
If the dPR has been fully approved,
it is ready for Purchasing and cannot be modified.
| Change | Procedure |
dPR Type Encumber Current or Next FY? | If screen 29H has not been completed and a dPR number has not been assigned - TAB to the TYPE field and key in the correct dPR type or change the C/N code. If screen 29H has been completed - Go to screen 29Z, erase the dPR. Create a new dPR with the correct dPR type. |
| Order/Delivery Information | Go to screen 29H, make the appropriate changes. Press ENTER. The message "DPR Xxxxxxx HAS BEEN MODIFIED" displays. |
Account Number Object Code Percentage Amount |
Document Funding-Go to screen 29H, type the dPR number in the
DOCUMENT field. Press ENTER. TAB to the document funding section, make
the appropriate changes. Press ENTER. Retrailer and reapprove the dPR.
Line Item Funding - Go to screen 29L, type the dPR number in the
DOCUMENT field. Press ENTER until the correct line displays or TAB to the LINE field, type the line number and press ENTER. TAB to the ACCOUNT field, make the appropriate changes. Press ENTER. Retrailer and reapprove the dPR. NOTE: You cannot change from line item funding to document funding or vice versa. |
| Vendor Information | Go to screen 29V, type the dPR number in the DOCUMENT field. Press ENTER. Make the appropriate changes. Press ENTER. The message "DPR Xxxxxxx HAS BEEN MODIFIED" displays. |
Quantity Price | Go to screen 29L, type the dPR number in the DOCUMENT field. Press ENTER until the correct line displays or TAB to the LINE field, type the line number and press ENTER. TAB to the desired field, make the changes. Press ENTER. Retrailer and reapprove the dPR. |
Unit of Measure (UOM) Line descriptions | Go to screen 29L, type the dPR number in the DOCUMENT field. Press ENTER until the correct line displays or TAB to the LINE field, type the line number and press ENTER. TAB to the desired field, make the changes. Press ENTER. The message "DPR Xxxxxxx HAS BEEN MODIFIED" displays. |
| Add a line | Go to screen 29L, press ENTER until a blank line displays. Add the line. Retrailer and reapprove the dPR. |
| Erase/Delete a line | Go to screen 29L, type the dPR number in the document field. Press ENTER until the correct line displays or TAB to the LINE field, type the line number and press ENTER. TAB to the UPO field,If the dPR has NOT been
trailered, enter X (erase). Press ENTER. The line disappears from the dPR. If the dPR has been trailered, enter D (delete). Press ENTER. The line is flagged from deletion. Note that the EXTENDED PRICE field is blank. Trailer the dPR to adjust the encumbrance. |
| Erase/Delete a dPR | Go to screen 29Z, type the dPR number in the DOCUMENT field. Press ENTER. TAB to the ENTER OPTION field, If the dPR has been trailered: Enter L (line delete). Press ENTER. Trailer the dPR to reverse the encumbrance. If the dPR has not been trailered: Enter X if you have not added any lines. Press ENTER. Enter D if you have added lines. Press ENTER. |
| Approvals | Once an approval has been processed, it cannot be revoked. Go to screen 22N, add a notepad revoking the approval. |
Table 5 - Changing dPRs that have been fully
approved
This table outlines the procedures for changing certain information
on dPRs after they've been fully approved. Once a dPR has
been fully approved, it is ready for Purchasing to process.
If a change is needed, you can either ask
Purchasing to "unlock" the
dPR so that you can make the change or enter a notepad indicating
the change. Unlocking a dPR allows you to modify a fully approved dPR.
| Change | Procedure |
| Add a line item | Purchasing will unlock the dPR. After the change is made, retrailer and reapprove the dPR. |
| Change and/or add suggested vendors | Add a notepad and contact Purchasing. If Purchasing requested the change, you do not need to contact them. |
| Change the account number | Purchasing will unlock the dPR. After the change is made, retrailer and reapprove the dPR. |
| Change the attachment flag | Add a notepad and contact Purchasing. If Purchasing requested the change, you do not need to contact them. |
| Change the description of a line | Add a notepad and contact Purchasing. If Purchasing requested the change, you do not need to contact them. |
| Change the ordered by and/or delivery information | Add a notepad and contact Purchasing. If Purchasing requested the change, you do not need to contact them. |
| Changing object codes | Either request that Purchasing unlock the dPR so that you can change the object code or add a notepad authorizing the object code change. If you change the object code, retrailer and reapprove the dPR. If you add a notepad, contact Purchasing. |
| Decrease the quantity and/or unit price | Add a notepad and contact Purchasing. If Purchasing requested the change, you do not need to contact them. |
| Delete a line item | Add a notepad and contact Purchasing. If Purchasing requested the change, you do not need to contact them. |
| Increase the quantity or the unit price | Purchasing will unlock the dPR. After the change is made, retrailer and reapprove the dPR. |
Table 6 - Changing dPRs when the PO exceeds the dPR
This table outlines the procedures Purchasing will use if the amount
of the PO will exceed the amount estimated on the dPR.
| The PO exceeds the dPR by | The dPR is | Action |
| < 1,000 | <= 200 | Buyer determines whether to continue or call the department. |
| > 200 | Buyer determines whether to continue or call the department. If the dPR is being processed in June on state accounts, the buyer must contact the fund accountant. |
| 1,000 - 10,000 | <= 10% | Buyer determines whether to continue or call the department. If the dPR is being processed in June on state accounts, the buyer must contact the fund accountant. |
| > 10% | Buyer unlocks the dPR and requests the department change the amount, thus forcing reapproval of the dPR. |
| > 10,000 | <= 1,000 | Buyer determines whether to continue or call the department. If the dPR is being processed in June on state accounts, the buyer must contact the fund accountant. |
| > 1,000 | Buyer unlocks the dPR and requests the department change the amount, thus forcing reapproval of the dPR. |