| 13-PROPERTY REPORTS |
|
| 13.20 FINAL PROPERTY REPORTS AND CLOSEOUT
|
EFFECTIVE
6/1/00 |
LAST UPDATE
12/01/02 |
|
| PURPOSE: |
To provide direction to university departments regarding the preparation and submission of
final property reports and completion of property closeout procedures on Sponsored
Projects. |
| AUTHORITY: |
Powers and duties of the University President, ABOR Policy 3-801 and 3-802
Below authority applies ONLY to Federal Property (acquisition dollars or title):
48 Code of Federal Regulations 45.505-14 AND 45.508-1
Office of Management and Budget Circular A-110
Terms and conditions of sponsor grants, contracts, and agreements with the University
|
| POLICY: |
Sponsored Projects Services is responsible for the preparation and submission of required
final property reports to sponsors and completion of property closeout procedures. The
requirements for the final property report are recorded in the Property Titleholder and
Reporting Database maintained by Sponsored Project Services.
Examples of sponsors requiring final reports include, but are not limited to the following:
(More sponsors require a final property report than an annual property report).
- NASA - All grants, contracts and cooperative agreements with or without equipment..
- JPL - All contracts with or with equipment.
- DoD - All grants and contracts with or without equipment
- DOE and its various laboratories - All grants and contracts
- John Hopkins University with DoD and NASA pass through requirements
- Other universities with DoD and NASA pass through requirements
- Arizona Disease Control and Research Commission - All grants
- Battelle Institution
- NOAA
- Arizona Department of Economic Security
- Public Health Service/National Institute of Health - Contracts.
- Wenner Gren Foundation
- Central Intelligence Agency
- Smithsonian
- Space Science Telescope Institute
When a sponsor request return of its furnished or titled equipment, the Principal Investigator is
to immediately return the equipment.
|
| PROCEDURE: |
| RESPONSIBILITY |
ACTION |
SPS PROPERTY ADMINISTRATOR |
- Continuously check the Data Sheet on all newly retired grants,
contracts and cooperative agreements for requirements for a final
property report.
- Print a listing of recently terminated contracts, grants and
cooperative agreements for each sponsor requiring a final report
from the Sponsored Projects Information System (SPINS)
databases. The list should be obtained at least quarterly, if not
more often.
- On each sponsor account requiring a final property report,
obtain property reports using the Property Database, a 9S
Financial Report from FRS, and titleholder information from the
Property Titleholder and Reporting Database. Reconcile the
financial report with the value of property included in the
Property Database. Reconcile the titleholder database
information with the title recorded for each asset in the Property
Database. Request corrections as necessary.
- When the final report is on a government contract, submit a
property inventory list to the Principal Investigator with
instructions to complete within 10 working days and return to
the SPS Property Administrator.
- Prepare and submit a final property schedule to the sponsor. Request relief of accountability, as necessary, for lost, missing or stolen items. If the final property schedule being submitted contains sponsor owned equipment, request disposition instructions with a primary emphasis of obtaining title for the University. If the equipment is government owned, request title under the Stevenson-Wydler Act or other appropriate statute or regulation. JPL and DoD final property schedules with government owned items require the use of a government condition code per item and the completion and attachment of Standard Form 1428 to the submitted property schedule.
- If there is no property to report, submit a negative closeout property report. If the report is on a JPL, NASA or DoD contract, submit a NASA 1018 to JPL and NASA, or a DoD Form 1642 to DoD facilities and offices.
- Upon issuance of disposition instructions by JPL, NASA, DoD and DOE contracts, complete and submit the following sponsor
closeout property report forms. All sponsor disposition
instructions are to be completed and the closeout report will be
negative.
- NASA and JPL use form NASA 1018
- DOD use form DoD 1662
- DOE use the form submitted with their report request
- John Hopkins and other universities use either NASA 1018
or DoD 1662 depending on the federal funding source.
|
PRINCIPAL INVESTIGATOR |
- If the sponsor request in its disposition instructions the return of
its furnished or titled equipment, it is to be immediately returned.
A copy of the receipt and shipping document is to be forwarded
to the SPS Property Administrator.
|
SPS PROPERTY ADMINISTRATOR |
- Follow up with sponsors to insure a timely response to any
request for disposition instructions. In the third request for
instructions, advise the sponsor that if a response is not received
within fifteen (15) days the University will consider the
equipment abandoned and that title has passed to the University.
- Update the Property Titleholder and Reporting Database with the 9S Financial Information, value of recorded property and date annual report submitted. Maintain copies of reports in the computer files of the sponsor and the grant, contract or agreement property folder.
- Prepare a Property Record Change Form to change title to the University when sponsor equipment is transferred, abandoned or given to the University. Direct the University department to remove all government or other sponsor identification by marking the box on the Property Record Change Form. Attach a copy of supporting documents and send to Property Management-FSO with a copy to the department and the Sponsored Projects Services property folder.
|
CROSS REFERENCE:
Return to Property Management Manual Contents
|